This was a conversion of an existing 15-unit residential building from electric baseboard to Mitsubishi Mini Split Heat pumps. The installation took place of a course of an 8-to-10-week schedule. The support rack and custom line set duct were fabricated in house by Day Square Plumbing and Mechanical Company. A Design Build Plumbing and Mechanical Company. Project: Columbus Ave., Boston South End